MAC House, Stockport

 

 

Pound
Project Value
£5m+
Crane
Industry Sector
Building and Development
Workman
Client Company
Westshield
Calendar
Project Timescale
24 Months
Westshield 44
Westshield 40
Westshield 41
Westshield 42
Westshield 38
Westshield 39
Westshield 43


Mac House is an apartment complex with character and kudos consisting of 74 one and two bedroom apartments split into 3 blocks that are stylishly designed, superbly kitted out in a great location, within the existing mill and in two new buildings. Designed in a complementary style and crafted using traditional materials to preserve the character and dignity of the development.

The Technical Aspect:

The works package comprised of:-

  • Sewer Diversion Works (Deep Drainage)
  • Demolition
  • Site Remediation
  • Piling
  • RC Beams
  • Foundations, Groundworks and Drainage
  • Timber Frame Structures and Traditional Masonry New Build
  • Renovation of Existing Mill with New Build Features
  • Brickwork (Cladding and Blockwork)
  • Car Parks
  • Traditional materials used, stonework/timber windows and slate roofs
  • Full Mechanical and Electrical Installation