Bury, Rochdale & Worsley WwTW

Project Value
£900,000+

Industry Sector
Water & Wastewater

Client Company
Advance Plus

Project Timescale
6 Months








Westshield working in partnership with Advance Plus for United Utilities. Self-delivering in numerous location within the works.
The Technical Aspect:
Westshield scope of works consisted of the following:
Rochdale:
- Mobilisation onto site
- Installation of Ferric Day Tank and Dosing Kiosk Base
- Footpaths
- Installation of Ferric Point of Application (POA) Plinths
- Installation of Cable Ducts and Drawpits
- Installation of Potable Water Pipework
- Installation of Final Effluent Water Pipework Extension
Bury:
- Mobilisation onto site
- Installation of Ferric Dosing Kiosk Base
- Installation of Potable Water Pipework Extension
- Installation of Chemical Blind Tank
- Installation of Three-Way Valve Chamber
- Installation of Tanker, Lay -by, Road Extension
- Installation of MCC Kiosk Base Slab
- Installation of Cable Ducts and Drawpits
- Installation of Wash Water Main Extension
- Installation of Point of Application Base Slabs (POA)
- Installation of Footpaths
Worsley:
- Mobilisation onto site
- Carry out Reduce Level dig
- Diversion of Recirc Main
- Installation of Silt Fencing
- Installation of Detention Tank MCC Slab
- Installation of Detention Tank
- Installation of Pumping Station
- Installation of Sludge Tank MCC Slab
- Installation of Ferric Dosing Base
- Installation of Caustic Dosing MCC Slab
- Blind Tank Installation
- Valve Chamber Installation
- Installation of Potable Water Pipework
- Installation of Sludge Tank Pipework
- Installation of Cable Ducts & Draw Pits
- Road & Local Hardstanding Installation